The structure of Org files---hierarchy and lists---makes it easy to
define TODO dependencies. Usually, a parent TODO task should not be
marked DONE until all subtasks, defined as children tasks, are marked
as DONE. And sometimes there is a logical sequence to a number of
(sub)tasks, so that one task cannot be acted upon before all siblings
above it are done. If you customize the variable
~org-enforce-todo-dependencies~, Org blocks entries from changing
state to DONE while they have children that are not DONE.
Furthermore, if an entry has a property =ORDERED=, each of its
children is blocked until all earlier siblings are marked DONE. Here
is an example:
marked DONE until all TODO subtasks, defined as children tasks, are
marked as DONE. And sometimes there is a logical sequence to a number
of TODO (sub)tasks, so that one task cannot be acted upon before all
siblings above it are done. If you customize the variable
~org-enforce-todo-dependencies~, Org blocks entries from changing state
to DONE while they have TODO children that are not DONE. Furthermore,
if an entry has a property =ORDERED=, each of its TODO children is
blocked until all earlier siblings are marked DONE. Here is an
example:
#+begin_example
,* TODO Blocked until (two) is done